The 2024-2026 restoration

Between 2024 and 2026 the Town Council carried out the most ambitious intervention ever undertaken at the fortress, funded by the European Union’s Recovery, Transformation and Resilience Plan.

In figures

  • €2,991,241

    Total amount of the project, 100% funded by the NextGenerationEU programme

  • 28 May 2026

    End of the bulk of the consolidation works, within the grant timetable

  • 4 finds

    Medieval floors, storage pits, an olive-oil mill and a buried chamber in the keep

  • 360°

    New viewpoint at the top of the keep, over the delta of the Tordera river

Funding

The castle’s conservation and restoration project receives funding from the Programme for improving competitiveness and revitalising historic heritage for tourist use, run by the Ministry of Industry and Tourism and approved by Order ICT/1363/2022.

The programme is part of the Recovery, Transformation and Resilience Plan (PRTR), funded by the European Union – NextGenerationEU. The total amount is €2,991,241.00, 100% grant-funded.

In April 2026 the Local Government Board approved an internal redistribution of the budget lines for unforeseen technical reasons, without changing the total amount or the purpose of the grant.

The NextGenerationEU project on palafolls.cat (in Catalan)

Timeline of the works

  1. January 2024

    The castle closes for six months for the restoration works.

  2. 23 December 2024

    The Ministry of Industry and Tourism publishes the final proposed decision on the grants under the historic heritage for tourist use programme.

  3. May 2025

    The castle closes again for a new phase of works, until March 2026.

  4. November 2025

    Award of the consolidation and reconstruction works, with a budget of more than €1.5 million.

  5. Early 2026

    The Ministry of Tourism grants an extension of the works until 31 May 2026.

  6. 28 May 2026

    The bulk of the works is completed, within the grant timetable.

  7. After May 2026

    The Town Council continues the fitting-out with its own resources: enclosures and an access-control booth.

  8. 9-12 October 2026

    Official inauguration ceremony and reopening to the public.

What has been found

The excavations have uncovered chambers, stairs and circulation spaces unknown until now, after tonnes of rubble and sediment were removed. Among the most significant discoveries:

  • Several floors from the medieval period
  • Storage pits
  • An olive-oil mill
  • A buried chamber in the keep, intact for centuries

What has been done

  • Great hall

    Rebuilt on the same site as the castle’s former hall, as a multi-purpose space for cultural and museum activities.

  • 360° viewpoint

    At the top of the keep, with views of the Tordera delta and the surrounding coastline.

  • Visitor route

    Accessible walkways and paths that let visitors tour the site while preserving the original structures.

  • Tower and walls

    Structural consolidation of the keep and reinforcement of the most weakened walls and stretches of wall.

The works on video

  • Playing the video loads it from YouTube (Google), which may store data in your browser.

  • Playing the video loads it from YouTube (Google), which may store data in your browser.

Photographs of the works

  • Structure of the new viewpoint with scaffolding, 2026
    Ajuntament de Palafolls · May 2026
  • The great hall with its new battlements, 2026
    Ajuntament de Palafolls · May 2026

European and local funding

  • Funded by the European Union – NextGenerationEU
  • Recovery, Transformation and Resilience Plan
  • Government of Spain, Ministry of Industry and Tourism, Secretariat of State for Tourism
  • Palafolls Town Council